A long job as it required :

  • Level out a sloping area (dig out and build walls) - 2 weekends work!
  • In-fill the base with rubble, an opportunity to break up more of the foundations of the old extension and bury it !, hard labour and three weekends work.
  • Get a mini-mix to lay the concrete slab (I wasnt doing that whole area with a mixer)
  • Get the Workshop built by the supplier Williams Sheds (3 weeks) delivered and installed (a weekend)
  • Then empty the house of all the tools, wood, workbenches, ladders, lime, sawdust !!!!
  • Paint it, Install electrics, lighting, guttering, security etc.
  • Build workbenches on three walls, including a recessed area for the Chopsaw.(picture #3)
  • Finally build Stone steps up to the side door.
I enjoyed tidying up my tools and now we are ready to go !!!!